Clearwater Beach / Sand Key
Clearwater Barrier Island
Clearwater Beach and Sand Key are barrier island properties subject to CCCL permitting through Florida DEP for work within approximately 300 ft of mean high water — adds 30–90 days to any project touching the shoreline zone. FEMA AE and VE flood zone designations cover most parcels. Marine-grade irrigation components and salt-tolerant plant selections required throughout. PM initiates CCCL process at project start, not after design is finalized.